90 DAY CONTAINMENT PAD

GIANT RESOURCE RECOVERY

HAZARDOUS WASTE CONTAINMENT

Our team successfully completed a 90-day containment pad project for hazardous waste storage containers, featuring a 12" thick reinforced slab and sump pit and steel railings for optimal fall protection. A surprise discovery of an unmarked underground utility required some mid project course correction, but we were able to consider a few options from an engienering perpsective and proceed with the most cost effective change to keep the project on track. This proactive adjustment ensured the project's completion on schedule, exemplifying our commitment to delivering high-quality, safe, and efficient solutions through our comprehensive design and construction services.